New States SIG - 2024-05-15
Participants
WebEx Recording LINK https://edfi.webex.com/edfi/ldr.php?RCID=bcce854bf9a45ccdc03f319220dc547
Agenda and Notes
Introductions and purpose of SIG meeting
Customer Success Team - Kathleen, Mike, and Steven
Welcome Christopher from Kansas and Eric from Tennessee
Topics from Tech Congress
SEAs Internal Departmental Engagement
Links to Academy courses
ICF for SEA - https://docs.google.com/spreadsheets/d/1Ufe5PB7959H5hA3lqmp6ToFl4dtOO1rf/edit#gid=282245608
Kathleen and Mike working on a project plan template for states starting to implement Ed-Fi
Texas - challenge during Pilot and Parallel Phases for asking commitment and timing for LEA to participate for end to end testing
Large, medium, small district bring different use cases for testing
Allow opportunity for testing in Pilot phase to identify issues
Vendors would like to be involved with state communications from the beginning
Vermont - when you use small medium and large, is this a relative term. for instance to some other states all our districts are small?
Kathleen - medium and large are relative, especially in large state like Texas
Look at sizes of your LEA, pick some of the bigger LEAs versus smaller LEAs
Kathleen - How did Vermont pick LEAs for participation in Pilot?
Vermont - we had 4 vendors in entire state
We went with PowerSchool that had most of the districts
At the end of the Pilot, small LEAs work with a small vendor called Alma. They are participating in the Parallel phase but have a long way to go.
Kathleen - difference between LEA participating in Pilot versus Parallel
Pilot - identify big hurdles that need to be corrected early on
Enhance, correct
Parallel - the more participation, the better Production will be. Best if 100% LEA participation, but at least 50%.
New issues will be identified, e.g. how to submit data through the API
First time LEA to receive data error back, learn how to use SIS error reporting to get errors corrected
Review state validation report, and how to make correction
Learn how to submit data, how to ask questions, how to communicate with the state and vendors
Minimize Last Minute API Changes by Planning Ahead
Challenge from Texas
Lack of collaboration with downstream systems, if not part of planning/testing, they may be reason for needing the data model changes
State Status
Kansas - Will start Pilot soon
Tennessee - In Parallel
Utah - Setting up Sandbox
Vermont - In Parallel phase, will be in Production next year, collecting data from LEA
Next meeting: June 19, 2024