9.22.2020 Weekly Data Import multi-connection check-in
9.22.2020 Weekly Data Import multi-connection check-in
Attendees
Ed-FI
Certica
Headspring
Agenda
- Status of last week's action items
- Status of current sprint scope
- Work completed since last check-in
- Work in progress
- Work remaining this sprint
- Confidence in ability to complete sprint scope on time / estimated time to done
Discussion
- Alex and Gary provided status of sprint 2 scope and are confident all scope will be completed on time (by end of day 9/29)
- Only one two-point story to validate multi-connection support remains outside of sprint 2 scope, and Alex estimates it will be be completed in the first three days of sprint 3, which means all development will be complete by ~10/5
- Gary provided overview of proposed Data Import PowerShell preprocessor enhancements documented in - EDFI-411Getting issue details... STATUS
Action Items
This Week
- lee.morrow to inform Patrick of upcoming PRs in sprint 2, and final review on or near 10/5
- Alex Kichkailo (Unlicensed) and Patrick to determine how best to manage any merges/merge conflicts for the upcoming muli-connection support PRs
- Jason Hoekstra to review Data Import PowerShell preprocessor enhancements proposed by Gary in - EDFI-411Getting issue details... STATUS and provide feedback during next week's check-in
Last week
- lee.morrow to mark EDFI-396 as unblocked
- Gary Clarke to document changes resulting from solutioning of EDFI-398 in story and design document
- Gary Clarke to create placeholder epic for PowerShell preprocessor work in the backlog detailing the scope of work for consideration in future release.
- lee.morrow to troubleshoot adding points field to DI tickets and notify Gary of outcome. If the field is added Gary will enter the point estimates. If Lee cannot add field Gary will comment point estimate on ticket.
Reference Material
- DI: Multi-connection board
- DI multi-connection support epic
- DI multi-connection support design document and meeting notes
, multiple selections available,
Related content
9.1.2020 Weekly Data Import multi-connection check-in
9.1.2020 Weekly Data Import multi-connection check-in
More like this
8.25.2020 Weekly Data Import multi-connection check-in
8.25.2020 Weekly Data Import multi-connection check-in
More like this
9.16.2020 Weekly Data Import multi-connection check-in
9.16.2020 Weekly Data Import multi-connection check-in
More like this