9.16.2020 Weekly Data Import multi-connection check-in
Attendees
Ed-FI
@Jason Hoekstra (Deactivated)
Certica
@Gary Clarke
@Alex Kichkailo (Unlicensed)
Headspring
@lee.morrow
@Patrick Lioi (Deactivated)
Agenda
Gary and Alex summarize the design decisions/changes made during Sprint 1 for Patrick's understanding
Gary, Alex, Patrick Unblock EDFI-396
Gary and Alex open questions for Patrick from story definition?
Team sprint 1 review / retro
Team do future sprint planning
Estimate remaining stories
Commit stories to Sprint 2
Rough plan and timeline for getting to done
Discussion
Sprint 1 design decisions
Gary and Alex briefed Patrick on the below design decisions and reviewed the corresponding changes in the design document.
Data model should refer to ApiServers rather than ApiConnections (see EDFI-406)
Agent deletion behavior (see EDFI-394)
Alex's bug fixes
Unblocking EDFI-396
Gary and Patrick confirmed this is unblocked. Lee to mark story as unblocked.
Open questions from definition
EDFI-398
Addressed two question posed by Gary in the story. Gary will update story and design doc where necessary.
New scope
EDFI-406
PowerShell preprocessor work for consideration to include in a release following 1.1.0
Gary and Alex will develop draft design document and share with team for review / feedback.
Gary to create placeholder epic in the backlog detailing the scope of work for consideration in future release.
Sprint 1 retro/review
Done
EDFI-375
In Review
EDFI-392
EDFI-393
Carry-over to Sprint 2
EDFI-394
EDFI-373
What can be improved?
Start using a single sprint board as the source of truth
Estimate remaining stories to improve ability to complete sprint scope
Future sprint planning
Sprint 2
Gary and Alex committed the below stories to sprint 2. This is all the remaining scope required for the DI 1.1.0 release. They feel confident they can deliver on the commit given Alex's bandwidth has doubled from %50 to 100% from sprint 1 to sprint 2.
EDFI-394 - In development - carryover from sprint 1
EDFI-373 - In development - carryover from sprint 1
EDFI-398 - Ready for development
EDFI-396 - Ready for development
EDFI-395 - Ready for development
EDFI-397 - Ready for development
EDFI-406 - Ready for development
Estimated time to completion
Gary estimates they will be able to be release ready by the end of sprint 2 / week 1 of sprint 3 at the latest.
Action Items
Reference Material